Building & Construction Disputes
Builder or Contractor Dispute — Know Where You Stand
Disputes between homeowners, developers, and builders can escalate quickly — especially when security of payment laws give contractors powerful statutory rights to recover money fast. Understanding your position under the contract and under the Security of Payment Act is critical before you respond to any claim or make any payment.
⚠ Payment claims under Security of Payment legislation must be responded to within 10 business days — missing this deadline can result in a default judgment against you for the full claimed amount — submit your request now.
Does This Sound Like You?
Common builder and contractor disputes we help with.
Builder demanding more money mid-project
Your builder has stopped work and is demanding additional money above the contract price before they will continue. You're not sure whether the extra costs are legitimate, whether the contract allows for them, or whether you have any right to withhold payment while the dispute is resolved.
Disputes about variations to the contract
The builder is claiming payment for variation work that you either didn't authorise, didn't agree to in writing, or believe is included in the original scope. You're concerned about how to dispute a variation claim without exposing yourself to a payment claim adjudication or litigation.
Contractor has walked off the job
Your contractor has stopped attending site without written notice and will not respond to your calls. You are not sure whether they have technically abandoned the contract, what steps you need to take before engaging another contractor, or whether you can recover any additional costs from the original builder.
Works do not comply with the contract or plans
The work completed by the builder does not match the approved plans, the specifications in the contract, or the Building Code of Australia. The builder is disputing the non-compliance, demanding progress payments, or threatening to claim under the Security of Payment Act while you are trying to get the work fixed.
Builder threatening a construction lien or caveat
Your builder or a subcontractor is threatening to lodge a caveat or construction lien over your property for unpaid amounts. A caveat on title can prevent you from selling or refinancing your property, and you need urgent legal advice on whether the threatened caveat is legitimate and how to respond.
Payment claim served under Security of Payment laws
A contractor has served you with a formal payment claim under the Building and Construction Industry Security of Payment Act (SOPA) and you have a very short window to serve a payment schedule in response. If you do not respond correctly and in time, you can be liable for the full amount claimed without any further hearing.
How It Works
Resolving a builder dispute starts with understanding your rights under the contract
Submit the details of your dispute and any payment claims you've received. A construction law specialist will review your contract, advise on your obligations under SOPA, and help you respond within the strict statutory timeframes that apply.
Submit Your Builder Dispute RequestSubmit your request
Tell us about the dispute, whether you have received a payment claim, the contract type, and what stage the project is at. Attach the payment claim and contract if you have them.
Lawyer reviews your contract and SOPA obligations
Your lawyer analyses the contract terms, assesses whether the payment claim is valid, and advises on your right to issue a payment schedule disputing the claimed amount.
Payment schedule served and dispute managed
Your lawyer prepares and serves the payment schedule, manages the adjudication process if it proceeds, and handles any follow-on litigation or tribunal application to resolve the underlying dispute.
10 Days
Maximum time to serve a payment schedule under SOPA after receiving a payment claim — missing it can be catastrophic
All 8 States
Requests matched to specialist lawyers across every state and territory in Australia
Free
Initial consultation — understand your rights and options before committing to any action
SOPA & VCAT
Our lawyers handle SOPA adjudications, VCAT building lists, NCAT applications, and QCAT building disputes
Before You Respond
Practical questions about builder and contractor disputes.
How do Security of Payment laws work in Australia? +
Each state and territory has its own Security of Payment Act — in NSW it is the Building and Construction Industry Security of Payment Act 1999, and equivalent legislation exists in Victoria, Queensland, Western Australia, and other jurisdictions. These laws give contractors, subcontractors, and suppliers a fast-track statutory right to recover progress payments for construction work or related goods and services. The regime operates independently of the contract — a party can serve a payment claim, and if the recipient does not serve a valid payment schedule in time, the claimant can proceed to adjudication or even enforce the debt in court without a full hearing on the merits.
How do I respond to a payment claim served under SOPA? +
You must serve a payment schedule within 10 business days (in most jurisdictions) of receiving the payment claim, or within a shorter period if specified in the contract. The payment schedule must identify the scheduled amount you agree to pay and, if that amount is less than the claimed amount, set out your reasons for withholding payment. If you fail to serve a payment schedule in time, the claimant can proceed to court to recover the full claimed amount as a debt, or commence adjudication. A lawyer should review the payment claim immediately to confirm it is a valid SOPA claim and to draft a compliant payment schedule.
What is the adjudication process under SOPA? +
If a payment dispute is not resolved after the exchange of payment claim and payment schedule, the claimant may apply to an authorised nominating authority to have the dispute adjudicated. An independent adjudicator is appointed who considers written submissions from both parties — there are strict time limits for submitting an adjudication response. The adjudicator determines the adjudicated amount, which is provisionally binding and can be enforced as a judgment debt. The losing party can pursue a later court proceeding to finally determine the underlying payment dispute, but must pay the adjudicated amount in the meantime unless they obtain a stay.
When can a homeowner terminate a building contract? +
Termination rights depend on both the contract terms and the general law. Most building contracts (including standard HIA and MBA forms) contain specific termination provisions that set out grounds for termination and notice requirements. Under the general law, a party can terminate for repudiation — where the other party has made clear they will not or cannot perform their obligations — or for serious breach. Purporting to terminate a building contract incorrectly can itself amount to repudiation, exposing you to a significant damages claim. Always get legal advice before issuing a termination notice.
Can I withhold the retention deposit if there are defects or disputes? +
Retention moneys are amounts withheld from progress payments under the contract as security for the builder's obligations, including defect rectification. Most standard building contracts allow a retention percentage to be held until the end of the defects liability period. Whether you can withhold a retention against a particular dispute or defect claim depends on the contract terms and what the retention is expressly securing. Simply refusing to release retention moneys without contractual justification could expose you to a valid SOPA payment claim. A lawyer can advise on the contractual mechanism for retaining funds and how to document your reasons.
Which body handles homeowner vs builder disputes — Fair Trading, VCAT, or the courts? +
The appropriate forum depends on your state and the nature and value of the dispute. In Victoria, residential building disputes are handled in VCAT's Building and Property List. In NSW, NSW Fair Trading provides a dispute resolution service and, failing that, NCAT handles residential building disputes. In Queensland, QCAT handles domestic building disputes. For commercial construction disputes, adjudication under SOPA and the Supreme Court are common forums. In many states, a complaint to the relevant building authority (e.g., VBA in Victoria, NSW Fair Trading) is also possible and can result in rectification orders being made against the builder.
Have a question not covered here? Submit your request and a lawyer will be in touch.
Request a Free Consultation